Aerial view looking down a lattice crane boom at night with city lights below and rigging cables catching amber sodium-vapor glow
One-Operator · Certified to 160 Tons · Available 24 / 7

Every lift is engineered
before the outriggers
touch dirt.

Tight residential lots. Heritage restoration lifts. Midnight hospital HVAC sets where the margin between the parapet and the power line is measured in inches.

4,200+
Incident-Free Lifts
36 hrs
Avg. Mobilization
160T
Certified Capacity
01Commercial · Chicago, IL
The Obstacle

A 12-story rooftop with no crane pad and a 3-day window.

The mechanical sub needed four rooftop AHUs — each 8,400 lbs — set on a 12-story building in the River North corridor. Street frontage was 28 feet. Two lanes of Michigan Avenue traffic. The previous operator walked after the site survey.

The Execution

A 200-ton hydraulic crane, a 3am street closure, and a lift plan that accounted for every inch.

We coordinated a CDOT street closure permit, set up on the sidewalk footprint using timber mats rated for the outrigger load, and executed all four picks between 2am and 6am — clear before morning commute. Zero incidents. Mechanical sub back on schedule.

Lift Plan Extract
Crane
Liebherr LTM 1200-5.1
Gross Load
8,400 lbs × 4
Max Radius
62 ft
Ground Bearing
6,200 psf verified
Wind Limit
22 mph abort
Duration
3hr 48min total
Why the previous operator walked

Street closures require CDOT permits, traffic control plans, and a certified flagger setup. Many operators don't maintain these relationships. We do — because the job doesn't start until the street is cleared.

Request a Lift Plan
Commercial crane operation at night on a Chicago street with city lights and rigging cables visible
Rooftop HVAC unit being lowered into position on a commercial building
Michigan Ave set, 3:22am. All four picks complete before first L train.
4,200+
Incident-Free Lifts
Since 2008
36 hrs
Avg. Mobilization
From first call
160T
Certified Capacity
Single-crane pick
Tight residential crane operation with limited clearance between structures and mature trees
Steel beam rigging setup showing spreader bar and load configuration
Evanston set. 4 ft 2 in clearance. The oak is still standing.
02Residential · Evanston, IL
The Obstacle

A 22-foot lot. A 40-ton steel beam. A heritage oak that couldn't be touched.

The structural engineer on a gut rehab specified a 42-ft W14×90 transfer beam through a gap between the neighbor's garage and a 140-year-old bur oak. The arborist said the root zone extended 18 feet from the trunk. The setback left us 4 feet of working clearance.

The Execution

A knuckle-boom picker, a custom spreader bar, and a 6-hour lift window timed to soil conditions.

We specified a 50-ton knuckle-boom crane that could fold its boom under the oak's lower canopy, custom-fabricated a spreader bar to control the beam's swing arc, and scheduled the lift for early morning when overnight rain had firmed the adjacent soil to its peak bearing capacity. The oak lost zero branches.

Lift Plan Extract
Crane
Manitowoc MLC50 Knuckle
Beam Weight
11,340 lbs
Working Clearance
4 ft 2 in
Soil Bearing
Post-rain 4,800 psf
Spreader Bar
Custom 28 ft fabricated
Root Zone Margin
6 in minimum
Why soil bearing capacity matters more than you think

A crane's outrigger pads transmit enormous point loads — a 50-ton crane can apply 180,000 lbs to a 4-square-foot pad. Saturated soil can fail silently. Timing the lift to post-rain conditions sounds counterintuitive, but overnight drainage firms clay soils to their peak bearing in the early morning.

Request a Lift Plan
0
Jobs Walked Off
After site survey
48 states
Operating Range
Licensed & insured
$5M
Liability Coverage
Per occurrence
03Tandem Lift · Milwaukee, WI
The Obstacle

A 190,000-lb transformer. Two cranes. Three agencies. One shot.

A utility substation upgrade required setting a 95-ton power transformer that had to be lifted over an active 138kV transmission line, set through a 22-foot gate opening, and lowered onto a foundation with ±1-inch tolerance. No single crane in the region had the capacity. The transformer could not be re-lifted if set incorrectly.

The Execution

A synchronized tandem lift, a custom rigging frame, and 14 weeks of pre-planning.

We coordinated two 300-ton cranes in a tandem configuration, designed and fabricated a custom equalizing beam to balance the asymmetric load, and worked with WE Energies, WDOT, and the Milwaukee County Sheriff to execute a 4-hour road closure on a state highway. The transformer landed within 3/8 inch of centerline on the first attempt.

Lift Plan Extract
Configuration
2× Liebherr LTM 1300-6.2
Gross Load
190,000 lbs
Combined Capacity
600 tons at radius
Placement Tolerance
±1 inch
Agencies Coordinated
WE Energies, WDOT, MCSO
Pre-Planning
14 weeks stamped plans
What makes a tandem lift different

In a tandem lift, load distribution between cranes shifts dynamically as the load swings. If one crane takes more than its share of the load at any point, both cranes are at risk. The equalizing beam is what prevents this — it's not standard equipment. We fabricated ours to the specific load geometry of this transformer.

Request a Lift Plan
Two large cranes performing a synchronized tandem lift operation at a utility substation
Road closure setup with traffic control for heavy crane operation on state highway
Milwaukee tandem set. 190,000 lbs. Landed 3/8 in from centerline.
What We Handle

The lifts other operators
won't quote.

Specialty crane work requires more than tonnage — it requires an operator who has engineered their way through the same constraint before.

Confined-Site Picks

Zero-clearance setups in residential lots, heritage courtyards, and interior atriums where standard crane footprints don't fit.

Off-Hours & Emergency

Midnight hospital HVAC sets, weekend structural steel, emergency picks when the schedule can't wait for business hours.

Heritage Restoration

Stone pinnacles, copper roofing panels, stained glass assemblies — material that can't be replaced lifted by an operator who understands the cost of error.

Tandem & Multi-Crane

Coordinated tandem lifts with road closures, traffic control, and multi-agency permits handled from first call to final bolt.

Engineered Lift Plans

Every job starts with a stamped lift plan: ground bearing analysis, radius charts, load path, and contingency protocol. Not a verbal walk-through.

OSHA & Insurance Ready

Full OSHA compliance documentation, $5M liability coverage, and operator certifications on file — ready for GC pre-qualification packets.

What a Lift Plan Actually Contains

The document most
contractors never see.

A lift plan is a legal document that specifies every parameter of a crane operation before it begins. We provide a stamped plan on every job — not because we're required to, but because improvisation is how incidents happen.

"The margin between the parapet and the power line was 14 inches. We had it measured three times before the crane left the yard."

— Operator, St. Francis Hospital HVAC Set, Chicago IL
Request a Lift Plan
01

Ground Bearing Analysis

Before any crane moves, we pull soil bearing reports or commission a geotechnical assessment. Outrigger loads are calculated against confirmed ground capacity — not estimated.

02

Radius & Capacity Charts

Every crane has a load chart that degrades with radius. We plot the pick point, the set point, and every intermediate position to confirm the crane stays within rated capacity throughout the swing arc.

03

Wind Speed Thresholds

Lifts have operational wind limits — typically 25–30 mph for standard picks, lower for large surface-area loads. Our plans specify the abort threshold and the protocol when conditions approach it.

04

Load Path & Exclusion Zones

The load travels a defined path. Every structure, utility line, and occupied area beneath that arc is mapped. Exclusion zones are established and communicated to site supervision before the hook is rigged.

05

Contingency Protocol

What happens if the load needs to be set down mid-swing, or if a tag line breaks? The plan answers these questions in advance — not in the moment when the margin is measured in inches.

Get Started

Request a
Lift Plan.

Tell us what you're moving and where. We'll respond with a preliminary lift plan assessment within 2 hours — no commitment required.

Why Contractors Trust Us
4,200+
Incident-free lifts
36 hrs
Average mobilization
160T
Certified capacity
0
Jobs walked off
Rigging Safety Checklist

28-point pre-lift checklist used on every job. Useful for GCs vetting crane operators and understanding what a thorough site survey looks like.

Emergency lift? Call direct: (312) 555-0194